Uzbekistan reconstructs 540.9 km of electricity supply lines
22/11/2013 13:18
Uzbekistan reconstructs 540.9 km of electricity supply lines
22/11/2013 13:18
Tashkent, Uzbekistan (UzDaily.com) -- Uzbekenergo state joint stock company reconstructed 540.9 km of electricity supply lines in ten months of 2013.
In ten months of 2013, the company also reconstructed 314 transformer points, built 299.5 km of electricity networks, and installed 236 transformer points. Over 130 billion soums were directed to implement these works.
The company repaired .4-110 kV transmission lines with the length of 20,000 km, over 6,000 transformer points, and about 80 sub-stations. About 20 billion soums were directed to implement these projects.
Enterprises of backbone grid invested over 6 billion soums to overhaul 110-500 kV high voltage electricity lines with the length of 800 km, six power transformers with the capacity of 35-500 kV, and 150 transformers with capacity of 110-500 kV.
Uzbekenergo said that it also replaced old transformers with new high capacity ones. All these measures helped to improve electricity supply 15,000 wholesale consumers and 1 million population.
New transformers were installed to replace old ones in Tashkent city, Khorezm, Surkhandarya, Samarkand and Bukhara regions, which also helped to improve water and energy supply to population.
New 200 transformer stations were installed at new blocks in rural areas, where individual houses on standard projects were constructed. At the same time, the company built 230 km of electricity supply lines with the capacity of 0.4-10 kV.
Within the project “Creation of joint venture on production of LED lamps in Angren special industrial zone”, the joint venture was created and it is expected that the first products will be produced in December 2013.
The project “Construction of high voltage line with the capacity of 500 kV “Talimarjan thermal power station – Sogdiana sub-station” with open distribution network of the capacity of 500 kV at Talimarjan thermal power station is under implementation. Within the project, some 218 km of high voltage line was constructed. Currently, the work is underway on launch of open distribution network at Talimarjan thermal power station.