Uzbekistan approves feasibility study of Kandym gas processing plant
14/09/2015 00:23
Uzbekistan approves feasibility study of Kandym gas processing plant
14/09/2015 00:23
Tashkent, Uzbekistan (UzDaily.com) -- The Government of Uzbekistan approved a feasibility study of a project “Construction of complex of gas processing plant and construction of Kandym group of fields” (first phase).
The resolution of the Uzbek Cabinet of Ministers said that within the realization of the agreement on product sharing in relation to Kandym group of fields, Khauzak and Shady fields, as well as Kungrad field between Uzbekistan and consortium of investors – LUKOIL and Uzbekneftegaz, the investment project “Construction of complex of gas processing plant and construction of Kandym group of fields” with maximum annual mining of 8.1 billion cubic meters of gas is implemented.
The document said that the first phase of the project (2015-2018) envisages of construction of 77 project wells, construction of 6 multiple well platforms, two collection points, pipeline for gas export, camp, external infrastructure facilities, plant for gas processing of the Kandym group of fields with annual production capacity of 7.819 billion cubic meters of marketable gas, 134,360 tonnes of stable gas condensate and 212,900 tonnes of elemental sulfur.
The second phase of the project (2020 - 2029) stipulates construction of 21 wells, two multiple well platforms, two booster compressor stations at gas collection points of Kandym fields, electricity supply facilities, communication and transport infrastructure.
The third phase (2028-2032) envisages construction of 16 project wells of Khodji, Western Khodji, Akkum-Parsankul firlds with construction of three multiple well platforms, two collection points and two booster compressor stations.
Within the implementation of the first phase of the project, LUKOIL Uzbekistan Operating company and the consortium led by Hyundai Engineering Co., Ltd. (South Korea) signed a contract on supply of equipment, construction of gas processing plant and construction of Kandym group of fields on turn-key bases for US$2.662 billion.
The Government approved the feasibility study of a project “Construction of complex of gas processing plant and construction of Kandym group of fields” (first phase), which underwent all necessary expertise at the authorized bodies. The resolution said that the object should be commissioned in December 2018.
29/04/2024Read more