Tashkent, Uzbekistan (UzDaily.com) — Globalink Logistics has successfully completed the transportation of critical components for a combined heat and power station in Talimardjan, Uzbekistan.
According to the company, the project involved the transport of two engines, each weighing 130 tons, and four generators weighing 75 tons, which were delivered from Turkey to Kazakhstan by sea and river vessels, and then transported overland via a complex route to the construction site.
Despite low water levels, strong winds, and infrastructure challenges on land, Globalink’s industrial logistics division (IPU) successfully managed the task.
The team ensured the safe loading, securing, and transportation of the equipment, using a modern fleet of heavy transport vehicles and their own engineering expertise. Specialists carefully planned the route, identifying and overcoming any obstacles to ensure timely delivery of the equipment.