First of all, the company plans to resume mining of ore at Uzun field at Kochbulak deposit. The investment project will be implemented in 2012-2013, the company said.
The design estimates is developed by the State Unitary Enterprise “Uzbek Scientific-Research Institute of Geotechnology and non-ferrous metallurgy O’zGEORANGMETLITI”.
This year, it is planned to start construction of underground mine at Samarchuk field of Kyzul-Alma deposit. The construction works will be completed in 2015.
Another project is launch of mining works at Kayragach field in 2012-2014, which located in northern sloe of Kuramin spine. The field is located close to Angren Gold Extracting Plant (25 km) and copper smelting plant of AGMK (75 km), which will help produce goods without additional expenses. It is planned to construct underground mine on mining gold containing ores.
Two more projects will help to increase mining and processing ores. The company plans to utilize Dalnee field and construct crushing and conveyor complex at Kalmakyr mine.