Uzbekistan 17/04/2023 7-bekat of elevated metro station to be closed in the capital for one day
7-bekat of elevated metro station to be closed in the capital for one day

Tashkent, Uzbekistan (UzDaily.com) -- Test train traffic at 5 metro stations of the II stage of the "Aboveground Ring Line" of the Tashkent metro from Kuilyuk to the "Building Quarter" is being completed, Toshkent metropoliteni said.

In this regard, in order to technically connect these new stations with the stations built at Stage I, on 19 April, the movement of trains on the "7-bekat" of the Overground Ring Line (Qo'yliq) will be stopped.

On this day, train traffic will be organized between stations starting from "Do'stlik-2" to "6-bekat". Also, additional bus traffic from "6-bekat" and "7-bekat" will be organized for passengers.

 